During the 2003-2004 school year, the following major renovations were completed:

  • Agnes Jones Gallery The Agnes Jones Interior Architecture Gallery received $57,433 in Lab Modernization funds to renovate the lighting, floors and display area. (Agnes Jones Gallery 127 CPS)
  • The Anatomy Lab and adjacent classroom in 116 HEC is receiving a complete make-over summer 2004. Total cost will be $87,750.
  • New chairs went into CPS 210, 229, 230, 234 totaling $25,000.
  • New tables went into 233, extending it capacity to 70 for $2,375.
  • 116 CPS received a large technology upgrade of $10,472.
  • The lighting in the women's locker room in HEC was upgraded at $4,500
  • The parking lot in front of the entrance at Communicative Disorders will be expanded summer 2004; the college and Communicative disorders will pay $10,000 to allow for some college spaces.
  • 209 CPS was upgraded with new paint and sound baffling $2,500.
  • New furniture and lighting for the Brodhagen-Counsell room 027 HEC- $10,000.